BRIEF CASE FACTS
Client:
G.C.:
Metric Contracting Services Corp
Geotechnical:
Terraprobe Inc.
Structural:
Piles:
59 Chance Helical Piles
Loadings:
80 kN (18 kips)
Challenges:
Emergency Slope Stabilization
Toronto, ON, Canada
Road closure on Glenwood Crescent in Toronto caused by slope failure of the ravine required immediate emergency restoration. Terraprobe was contracted by the City of Toronto to complete a geotechnical investigation and design the slope stabilization repair. Terraprobe confirmed there was no further slope movement and that damage occurred in a localized area. EBS was contacted to supply and install Helical Anchors to stabilize the existing slope.
Tension Load: 80 kN (18 kips)
Depth: 4 to 14 metres
Total Number of Anchors: 59 Chance® Helical Piles